19
integrated works in 12 countries, about 74 Mt of steel a year
Weekly
status and brief every Monday, 08:00 CET
3 weeks
from the Salzgitter furnace stop in 2023 to the alert
Night-time VIIRS heat over the Salzgitter steelworks, 24 Jul – 20 Aug 2023, with blast furnace A off; 4-week index −28.4 percent
Week 33 · 14–20 Aug 2023 4-week index −28.4 % Blast furnace A off

4-week index, May 2023 – Mar 2024 · red shading: furnace off · dashed: −25 %, the outage line · grey: too few observations

Salzgitter steelworks: night-time VIIRS heat over four weeks, relative to normal for the time of year, over Sentinel-2 true colour. Blast furnace A, about half of the works' iron capacity, was off for relining from 1 Aug 2023 to 3 Jan 2024; the outage alert went out on 21 Aug.
VIIRS active fires: NASA FIRMS · Contains modified Copernicus Sentinel-2 data 2023

01 · STATUS BOARD

Every covered works, one line each.

Status comes from the 4-week heat index and its interval. Possible outage: at or below −25 % with the interval below zero for two weeks, until it is back above −10 %. Reduced: −15 % or lower, interval below zero. Not every possible outage is a real stop; the interval says how sure the reading is.

PUBLIC VIEW · WEEK 35, 2026 · 3 MONTHS DELAYED
Week 35, 2026 (24–30 Aug) · 4-week index: % vs normal for the time of year, with its 95 % interval on a −60 to +60 scale
WORKS OPERATOR MT / YR STATUS 4-WEEK INDEX LAST 52 WEEKS SEEN LAST WEEK
Duisburg-Huckingen (HKM)Germany Hüttenwerke Krupp Mannesmann 4.0 Possible outage since w23 2026 (1 Jun) −19.5 % (−38.4 to −0.6) 29 night passesVIIRS
DillingenGermany Dillinger / Saarstahl 4.0 Possible outage since w32 2026 (3 Aug) −13.6 % (−37.7 to +10.5) 12 night passesVIIRS
Dąbrowa GórniczaPoland ArcelorMittal Poland 2.5 Possible outage since w34 2026 (17 Aug) −36.9 % (−52.8 to −21.0) 16 night passesVIIRS
TarantoItaly Acciaierie d'Italia 2.0 Possible outage since w21 2025 (19 May) −42.9 % (−55.7 to −30.1) 20 night passesVIIRS
DuisburgGermany thyssenkrupp Steel 10.0 Normal −11.5 % (−26.7 to +3.7) 28 night passes · 1 clear sceneVIIRS · Sentinel-2 · Landsat
DunkerqueFrance ArcelorMittal 6.5 Normal −13.6 % (−32.2 to +5.0) 24 night passes · 2 clear scenesVIIRS · Sentinel-2 · Landsat
IJmuidenNetherlands Tata Steel Nederland 5.9 Normal −3.5 % (−21.8 to +14.8) 25 night passes · 2 clear scenesVIIRS · Sentinel-2 · Landsat
LinzAustria voestalpine 5.6 Normal −13.6 % (−28.6 to +1.4) 24 night passes · 5 clear scenesVIIRS · Sentinel-2 · Landsat
GentBelgium ArcelorMittal 5.0 Normal −10.7 % (−25.9 to +4.5) 25 night passesVIIRS
SalzgitterGermany Salzgitter AG 4.1 Normal −10.8 % (−26.5 to +4.9) 21 night passes · 1 clear sceneVIIRS · Sentinel-2 · Landsat
Fos-sur-MerFrance ArcelorMittal 4.0 Normal +5.1 % (−20.4 to +30.6) 29 night passesVIIRS
KošiceSlovakia U.S. Steel Kosice 4.0 Normal −5.7 % (−23.4 to +12.0) 26 night passesVIIRS
BremenGermany ArcelorMittal 3.5 Normal −4.8 % (−23.1 to +13.5) 19 night passesVIIRS
RaaheFinland SSAB 2.6 Normal −1.7 % (−28.1 to +24.7) 24 night passesVIIRS
TřinecCzechia Třinecké železárny 2.5 Normal −12.3 % (−42.6 to +18.0) 10 night passesVIIRS
LuleåSweden SSAB 2.0 Normal −4.5 % (−44.8 to +35.8) 24 night passesVIIRS
Gijón (Veriña)Spain ArcelorMittal 2.0 Normal +1.4 % (−41.1 to +43.9) 15 night passesVIIRS
AvilésSpain ArcelorMittal 2.0 Normal −20.0 % (−55.1 to +15.1) 11 night passesVIIRS
EisenhüttenstadtGermany ArcelorMittal 1.8 Normal +4.1 % (−38.6 to +46.8) 19 night passesVIIRS

Pilot users see the current week. Works and operators are named for identification only; Ferrosat has no link to any steelmaker. Capacities are approximate. 22 works are mapped; Donawitz, Ostrava and Galați are not yet on the board.

02 · THE WEEKLY BRIEF

What changed at Europe's blast furnaces, every Monday.

One e-mail: new possible outages, works back to normal, stops still running, and the European composite. Short enough to forward to your team. An alert follows the moment a works crosses the outage line.

  • Steel and raw-material analysts and tradersEuropean steel, iron ore, coking coal, scrap. Know which furnaces are running without piecing it together from press releases.
  • Suppliers and logistics to steelworksPellets, coke, ferroalloys, refractories, gases, rail and port. See when a customer's furnace stops, and when it comes back.
  • Credit and restructuringAn independent weekly read on works whose operators are under strain, where statements come late or not at all.
From: Ferrosat <brief@ferrosat.eu> · Monday 31 Aug 2026, 08:00 Week 35: one new possible outage, two works back to normal
NEW · POSSIBLE OUTAGE Dąbrowa Górnicza (ArcelorMittal Poland): 4-week index −36.9 % (−52.8 to −21.0), below −25 % for two weeks; since week 34.
BACK TO NORMAL Gijón (Veriña): event closed, +1.4 %. Duisburg (thyssenkrupp): no longer reduced, −11.5 %.
STILL OPEN Taranto, since week 21, 2025 (−42.9 %) · Duisburg-Huckingen, since week 23 (−19.5 %) · Dillingen, since week 32 (−13.6 %, recovering)
European composite, 19 works: −10.8 % (−15.9 to −5.7) Full status board
The brief as it would have gone out for week 35, 2026, from the published index.

03 · EVIDENCE

Known stops, found again from orbit.

Monthly index with its 95 % interval. Shaded: the stop as published by the operator or reported in the press. Dashed: −25 %, the outage line. A whole furnace off shows clearly; one furnace of several shows, but weaker.

SalzgitterAug 2023 – Jan 2024
−24 %
Blast furnace A relined, about half of the works' iron capacity. Jul 2022 – Jun 2024 · average in shaded months
IJmuidenApr 2023 – Jan 2024
−33 %
Hoogoven 6 relined, one of the works' two blast furnaces. Jul 2022 – Jun 2024 · average in shaded months
LinzAug – Oct 2023
−13 %
Blast furnace 5 relined, about 17 % of iron capacity: visible, but under the outage rule. Jul 2022 – Jun 2024 · average in shaded months
Tarantofrom May 2025
−44 %
Blast-furnace stop reported in May 2025; the possible outage is still open. Sep 2024 – Aug 2026 · average in shaded months

The European cycle, against official output

Ferrosat composite (19 works, capacity-weighted, shaded: 95 % interval) and Eurostat's EU production index for iron and steel, both as % vs the same month in 2022–25
Ferrosat Eurostat, EU
The two move together: r = 0.74 month by month, 0.90 on 3-month averages. Read it as a weekly view of the cycle, not a forecast of the next official number: month-to-month changes are mostly noise (r = 0.07). Oct 2021 – Aug 2026 · last public month: Ferrosat −6.1 %, Eurostat −0.8 % · Eurostat sts_inpr_m, NACE C24.1, calendar adjusted; includes electric-arc steel, which Ferrosat does not see
The close-up: Sentinel-2 and Landsat on clear days Where the nightly data say a works cooled, the 20 m and 30 m images show which yard.
Sentinel-2 heat over the Salzgitter steelworks, 12 to 18 June 2023, before the reline: several hot slag areas 12–18 Jun 2023 · running
Sentinel-2 heat over the Salzgitter steelworks, 4 to 10 September 2023, during the reline: the northern slag area and the centre of the works much cooler 4–10 Sep 2023 · furnace A off
Salzgitter, weekly mean shortwave-infrared heat. Clear weeks only: optical satellites cannot see through cloud, which is why the weekly status leans on the nightly VIIRS passes.
Contains modified Copernicus Sentinel-2 data 2023

Checked against outside numbers

EU composite vs Eurostat, monthly
r = 0.74
Same, 3-month averages
r = 0.90
Works vs verified CO₂ (EU ETS), yearly, 8 longest-covered works
r = 0.80
Interval check: weeks outside their 95 % interval
6 %
All checks, including the weak ones

The limits, stated plainly

  • A works-wide stop shows within two to four weeks. One furnace of several shows as a dip, often under the outage line.
  • Status is a reading, not a report: not every possible outage is a real stop.
  • Long cloudy spells widen the interval; it is shown, never hidden.
  • Blast-furnace works only: electric-arc furnaces are not covered.
  • History from mid-2021; the weekly releases kept as published since November 2026.
Read the methodology

04 · HOW IT WORKS

A running blast-furnace works is one of the hottest places you can see from orbit.

  1. STEP 1

    Satellites see the heat every night

    Molten slag and iron glow in shortwave infrared. Three VIIRS satellites pass every night; on a clear night with no heat at a works, that counts as cold, not as missing.

  2. STEP 2

    Close-ups on clear days

    Sentinel-2 (20 m) and Landsat (30 m) measure the slag yards outlined on each works, without using any output data. Heat elsewhere, such as hot slab stock, is left out.

  3. STEP 3

    Index, interval, status

    Each works is compared with the same time of year in 2022–25: a % above or below normal with a tested 95 % interval, then a status. Works roll up to countries and Europe.

05 · DELIVERY

The brief for reading, the data for your own models.

Weekly brief and alerts

Monday e-mail for the whole team, plus an e-mail or phone alert when a works crosses the outage line or comes back.

Data feed

CSV and a JSON summary in a cloud bucket with manifest and checksums: weekly and monthly index per works, country and Europe; outage events; works list. Parquet, API or Snowflake share on request.

Kept as published

Every Monday's release is stored unchanged, every change of method is logged, so you can always see what was known when.

Sample row, weekly.csv (public, delayed)
periodsiteindex_pctci_lowci_highindex_4w_pctyoy_pctn_viirsn_viirs_zeron_s2n_landsatstatus
2026-W35linz-0.7-25.424.0-13.6-20.824041final

Questions

A whole works or its main furnace going cold shows within two to four weeks: the 4-week index has to fall below −25 % for two weeks in a row. At Salzgitter in 2023, blast furnace A stopped on 1 August and the alert went out on 21 August.

06 · PILOT

Join the pilot

Ferrosat is in a free pilot. Pilot users get the weekly brief and alerts, the status history for all 19 works since mid-2021, and the methodology note. In return, we ask what you would use it for and what is missing.

Or write to data@ferrosat.eu

Free during the pilot. Pricing will be set with pilot users.

Behind Ferrosat: Gašper Kreft, Ljubljana. Studied computer science and mathematics, then worked as a data scientist at the Jožef Stefan Institute (IJS), analysing electricity consumption.

Used only to send the pilot brief and reply. See the privacy notice.